Happy Holiday Update from Your CCWD

Backhoe Sold - Money Deposited
The Backhoe check was credited to the CCWD Checking account Monday Dec 18th for $7,000.

Other Equipment
Daryl washed the Dump Truck (now named Betty) and took the Track Loader out for a spin on clean up day.
Audit Started
The bookkeeper, Jerry and Gunnar will be working the audit this week.
Education
Ellyn and Gunnar attended RCAC webinars on Rate Setting and Ellyn attended an additional webinar on Navigating State Funding in December.

Final Tank Parts Installed and Paperwork Package for the County DEH Presently Being Assembled
Summary of Tank Installation
● Onsite D1 oversight on all activities
● Installation aligned with County approved plans
● ALL parts are NSF-61 Compliant
● Overflow plumbing installed (diameter = 4 inches)
● Overflow uses #24 mesh (added reinforcement mesh)
● Tank water sampling plumbing installed
● Tank drain plumbing installed
● Tank isolation valves installed
● Tank water level gauge installed
● Tank and plumbing parts fully disinfected
● Bacteriological Lab Tested - Total and Fecal Coliform Absent
Happy Holidays to all!
CCWD Board