Five Summer Upgrades - New Well Pump, New Well Motor, Two New Valves and High Speed Internet
Success - Five Big Upgrades!
The water district with volunteers installed and upgraded the following:
- New Mooney well pump with higher pump rate
- New Mooney well motor with better electronics
- New main valve at Smoketree and Canyon with high quality plumbing parts
- New branch valve on Smoketree with high quality plumbing parts
- New high speed internet using Starlink
Special Thanks to: Our water manager Dean Kuns, Jerry Buchheit and plumber Robert Sexton for upgrading the Mooney pump and motor and replacing pipeline valves. Marsha Campbell and Chris MacDonald for Starlink installation. Ron Akey, Steve Fillmore and Chris MacDonald for vault digging and heavy equipment operations. All the water district board members for heavy equipment operations, digging, plumbing, installing Starlink, buying materials, research and oversight.
These upgrades are big and support a more reliable and maintainable water system. We welcome volunteers in the summer where work begins before the sun rises. These jobs required the following in the field work hours (does not include driving to the desert):
- Board Members - 90 hours
- Water Manager - 50 hours
- Volunteers - 30 hours
- Contractor - 30 hours